Toyota Venza manuals

Toyota Venza: Installation

INSTALLATION

PROCEDURE

1. INSTALL WATER PUMP ASSEMBLY

(a) Install a new gasket and the water pump with the 7 bolts.

Torque:

21 N·m {214 kgf·cm, 15 ft·lbf}


2. INSTALL V-RIBBED BELT TENSIONER ASSEMBLY


3. INSTALL GENERATOR ASSEMBLY


4. INSTALL WIRE HARNESS CLAMP BRACKET


5. INSTALL V-RIBBED BELT

HINT:

See page


6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:

When disconnecting the cable, some systems need to be initialized after the cable is reconnected (See page ).


7. ADD ENGINE COOLANT


8. INSPECT FOR COOLANT LEAK


9. INSTALL COOL AIR INTAKE DUCT SEAL


10. INSTALL NO. 1 ENGINE UNDER COVER

11. INSTALL NO. 2 ENGINE UNDER COVER

12. INSTALL NO. 1 ENGINE COVER SUB-ASSEMBLY


Removal
REMOVAL PROCEDURE 1. DISCONNECT CABLE FROM NEGATIVE BATTERY TERMINAL NOTICE: When disconnecting the cable, some systems need to be initialized after the cable is reconnected (See page ). 2. RE ...

1ar-fe Emission Control
...

Other materials about Toyota Venza:

Transfer Case Front Oil Seal(for Rh Side)
Components COMPONENTS ILLUSTRATION Replacement REPLACEMENT PROCEDURE 1. DRAIN TRANSFER OIL (a) Remove the transfer drain plug and gasket to drain the transfer oil. (b) Install a new gasket and the transfer drain plug. Torque: 49 N·m {500 kgf ...

System Voltage (P0560)
DESCRIPTION The battery supplies electricity to the ECM even when the ignition switch is off. This power allows the ECM to store data such as DTC history, freeze frame data and fuel trim values. If the battery voltage falls below a minimum level, the stor ...

Replacement
REPLACEMENT PROCEDURE 1. REPLACE INTAKE VALVE GUIDE BUSH (a) Heat the cylinder head to approximately 80 to 100°C (176 to 212°F). (b) Place the cylinder head on wooden blocks. (c) Using SST and a hammer, tap out the valve guide bush. SST: 0 ...