INSTALLATION
PROCEDURE
1. INSTALL FRONT NO. 3 SPEAKER ASSEMBLY (for 13 Speakers)
|
(a) Engage the 3 claws to install the front No. 3 speaker assembly. |
|
2. INSTALL FRONT PILLAR GARNISH CORNER PIECE (for 13 Speakers)
3. INSTALL FRONT NO. 2 SPEAKER ASSEMBLY
|
(a) Connect the connector. |
|
|
(b) Install the front No. 2 speaker assembly with the 2 bolts. Torque: 11 N·m {112 kgf·cm, 8 ft·lbf} |
|
4. INSTALL NO. 1 INSTRUMENT PANEL SPEAKER PANEL SUB-ASSEMBLY
5. INSTALL FRONT NO. 4 SPEAKER ASSEMBLY (for 13 Speakers)
|
(a) Connect the connector. |
|
(b) Install the center speaker assembly with the 2 bolts.
Torque:
11 N·m {112 kgf·cm, 8 ft·lbf}
6. INSTALL NO. 2 INSTRUMENT PANEL SPEAKER PANEL SUB-ASSEMBLY
7. INSTALL FRONT PILLAR GARNISH
8. CONNECT FRONT DOOR OPENING TRIM WEATHERSTRIP
Inspection
Luggage SpeakerProblem Symptoms Table
PROBLEM SYMPTOMS TABLE
HINT:
Use the table below to help determine the cause of problem symptoms.
If multiple suspected areas are listed, the potential causes of the symptoms
are listed in order of probability in the "Suspected Area" ...
Installation
INSTALLATION
PROCEDURE
1. INSTALL STARTER ASSEMBLY
(a) Install the starter with the 2 bolts.
Torque:
37 N·m {377 kgf·cm, 27 ft·lbf}
(b) Connect the starter connector.
...
Installation
INSTALLATION
PROCEDURE
1. CLEAN QUARTER WINDOW ASSEMBLY
(a) Clean the outer edges of the quarter window assembly with a non-residue
solvent.
NOTICE:
Do not touch the glass surface after cleaning it.
Be careful not to ...