INITIALIZATION
1. INITIALIZE POWER WINDOW CONTROL SYSTEM (POWER WINDOW REGULATOR MOTOR ASSEMBLY (ALL DOORS))
CAUTION:
When the power window regulator motor assembly is reinstalled or replaced, the power window control system must be initialized. Functions such as the auto up/down, jam protection, remote control and key-off operation do not operate if the initialization is not performed.
HINT:
When the battery is replaced, it is not necessary to initialize the power window regulator motor assembly.
NOTICE:
). (a) Initialization procedure when replacing the power window regulator motor assembly with a new one:
(1) Connect the battery and turn the ignition switch to ON.
(2) Fully open the window by fully pushing down the power window regulator master switch assembly or power window regulator switch assembly, and hold the switch for 1 second or more after the window is fully opened.
(3) Fully close the power window by fully pulling up the power window regulator master switch assembly or power window regulator switch assembly, and hold the switch for 1 second or more after the window is fully closed to reset the glass position and complete initialization.
(b) Initialization procedure when removing/installing the power window regulator motor assembly:
(1) Connect the battery and turn the ignition switch to ON.
(2) Fully close the power window by fully pulling up the power window regulator master switch assembly or power window regulator switch assembly, and hold the switch for 6 seconds or more after the window is fully closed (if the power window does not move or stops halfway even when the switch is fully pulled, release the switch and fully pull it again).
(3) Fully open the window by pushing down the power window regulator master switch assembly or power window regulator switch assembly, and hold the switch for 1 second or more after the window is fully opened.
(4) Release the power window regulator master switch assembly or power window regulator switch assembly. Then fully push down and hold the switch for 4 seconds or more.
(5) Fully close the power window by fully pulling up the power window regulator master switch assembly or power window regulator switch assembly, and hold the switch for 1 second or more after the window is fully closed to reset the glass position and complete the initialization.
(c) Initialization procedure when the power window does not fully open:
(1) Connect the battery and turn the ignition switch to ON.
(2) Fully close the power window by fully pulling up the power window regulator master switch assembly or power window regulator switch assembly, and hold the switch for 6 seconds or more after the window is fully closed (if the power window does not move or stops halfway even when the switch is fully pulled, release the switch and fully pull it again).
(3) Fully open the window by pushing down the power window regulator master switch assembly or power window regulator switch assembly, and hold the switch for 1 second or more after the window is fully opened.
(4) Release the power window regulator master switch assembly or power window regulator switch assembly. Then fully push down and hold the switch for 4 seconds or more.
(5) Fully close the power window by fully pulling up the power window regulator master switch assembly or power window regulator switch assembly, and hold the switch for 1 second or more after the window is fully closed to reset the glass position and complete the initialization.
Customize Parameters
Problem Symptoms TableInspection
INSPECTION
PROCEDURE
1. INSPECT COURTESY LIGHT SWITCH
(a) Measure the resistance according to the value(s) in the table below.
Standard Resistance:
Tester Connection
Switch Condition
Specified Condition
...
Inspection
INSPECTION
PROCEDURE
1. INSPECT FRONT LOWER BALL JOINT
(a) Inspect the turning torque of the ball joint.
(1) Secure the front lower ball joint in a vise using aluminum plates.
(2) Install the nut to the front lower ball joint stud.
(3) U ...
LVL Terminal Circuit
DESCRIPTION
By connecting terminals LVL and CG of the DLC3, the headlight leveling
ECU assembly initializes the height control sensor signal.
WIRING DIAGRAM
PROCEDURE
1.
CHECK HARNESS AND CONNECTOR (DLC3 - HEADLIGH ...